FLOW CHART FOR SINGLE FAMILY HOUSE CONSTRUCTION
|
Storm Water Permit for
Disturbance Over 10,000 Square Feet (100 x 100) Refer to By-law |
|
Possible wetlands within 150 feet of development activity? ** |
![]()
![]()
![]()
NO YES
|
Contact Conservation Commission to Determine if site is under
jurisdiction –
(Request for Determination
of Application) Usual time frame: 3 weeks* 323-0405 Room 101 Town Hall |
|
Negative Determination |
Positive Determination |
![]()
![]()
|
Submit Application for Wetland Permit for approval
to Conservation Commission (Notice of Intent) Usual time frame: 6 weeks |
|
Contact Health Department to have Perc Test performed. Time frame:
performed during months of March/April/May – schedule appointments Board of Health: 323-0406 Mon/Wed/Friday Office Hours 9:00 – 2:00 |
![]()
|
Submit Well Permit Plans
for approval to health officer. Usual time frame: 1 – 3
days (can take up to 21 days)* Submit Septic Design/Permit
Plans for approval to Board of Health.
|
|
|
|
|
Apply for Building Permit with Building InspectorDocuments Required:
2. Approved Storm Water Permit
4. Surveyed plot plan –will usually come with Septic Design 5. Energy Code Compliance: use REScheck Version 3.7lb Download at : www.energycodes.gov/rescheck 6. Two sets of house plans 7. Permit from Conservation Commission (Order of Conditions) Usual time frame: 1 business day (can take up to 30 days)* |
|
|
|
|